Concrete is a mix of cement, sand and aggregate (gitti) with water. The grade tells you the mix: M20, for example, is 1 part cement, 1.5 parts sand and 3 parts aggregate. This calculator works out how much of each you need for a slab, floor, footing or beam.
How to use the concrete calculator
- Enter the length and width in feet.
- Enter the thickness in inches (for example, 5 inches for a roof slab or 3 to 4 inches for a floor).
- Choose the grade.
For a beam or column, enter its length, width and depth the same way.
How it is calculated
Wet volume = length × width × thickness
Dry volume = wet volume × 1.54
Cement = dry volume × cement part ÷ total parts (1 m³ cement = 28.8 bags of 50 kg)
Sand = dry volume × sand part ÷ total parts
Aggregate = dry volume × aggregate part ÷ total parts
Water = cement weight × 0.5
| Grade | Mix | Common use | Cement per m³ of concrete |
|---|---|---|---|
| M10 | 1 : 3 : 6 | Levelling, PCC under footings | about 4.4 bags |
| M15 | 1 : 2 : 4 | Floors, paths | about 6.3 bags |
| M20 | 1 : 1.5 : 3 | Slabs, beams, columns (RCC) | about 8.1 bags |
| M25 | 1 : 1 : 2 | Heavily loaded RCC | about 11.1 bags |
Example
A roof slab 10 ft × 10 ft, 5 inches thick, in M20:
- Concrete volume: 10 × 10 × 5/12 = 41.7 cft (1.18 m³)
- Cement: about 9.5 bags
- Sand: about 17.5 cft
- Aggregate: about 35 cft
- Water: about 238 litres
Important
- These are nominal mixes. For M25 and stronger, and for any structural work, the Indian standard IS 456 recommends a design mix from an engineer.
- The 1.54 factor covers voids and shrinkage. Add 2 to 5% for wastage at site.
- Cure the concrete by keeping it wet for at least 7 days, and longer for slabs, to reach full strength.
FAQ
How many cement bags are needed for 1 cubic metre of M20 concrete?
About 8 bags of 50 kg for a nominal 1 : 1.5 : 3 mix.
What does M20 mean?
M stands for mix and 20 for the strength: 20 N/mm² after 28 days of curing.
How much water should I add?
A water-cement ratio of about 0.45 to 0.5 is typical, so about 22 to 25 litres per 50 kg bag. Too much water makes concrete weak.